LAGSTAFF GREEN
CONSTRUCTION UPDATE
15-31 BATMAN STREET, WEST MELBOURNE
NOVEMBER 2018
We are excited to advise building works at Flagstaff Green are on schedule.
Works are currently up to Level 19 floor slab with the lift core being disassembled over the coming weeks and the structure due to be completed by mid next month. Services are at Level 12, Sheeting is up to Level 7, glazing of windows are at Level 10 and Joinery have begun on Levels 2 & 3.
The vendor is anticipating construction completion in Mid 2019.
We will continue to update you as we receive communication from the vendor. If you have any questions in relation to your property and/or the above details, please do not hesitate to contact us.