CONSTRUCTION UPDATE : CAMBODIA Sunshine Hotel and Resort
Piling all done, now working on the footings and the boundary wall.
* Piling for building 100%
* Piling for retaining wall 93%
* Soil excavation of footings 42%
* Cutting head of pile in building area 45%
The construction crew working Sundays and evenings too at the moment to make sure we stay on schedule despite the recent rains causing extra work.